Document Page: First | Prev | Next | All | Image | This Release | Search
File: aaanx_01.txtSUBJECT: 1706 AREFWP ENGINEERING/FIRE PROTECTION/STATUS TO: DE DATE: 02-15-91 LGX TIME: 08:34 CC: SUBJECT: 141030ZFEB91 1706 AREFWP/DE PRIORITY: ATTACHMENTS: ---------------------------------------------------------------------------------------- RAASZYUW RHIDFKA03 0461128- -RHDIBFF. ZNY R 141030Z FEB 91 FM 1706 AREFWP//DE// TO RHIUFAA/HQ USCENTAF FWD//DE/LG// INFO RUCUAAA/HQ SAC OFFUTT AFB NE//SBS/DER/LG// RHDIAAA/HQ USCENTAF LANGLEY AFB VA//DE/LG// BT SUBJECT: ENGINEERING/FIRE PROTECTION/STATUS 1. (U) ENGINEERING A. PRIME BEEF: CURRENT: 57 PERSONNEL PROJECTED: 3 (1 EXTERIOR, 1 INTERIOR, AND 1 CARPENTER) B. WATER STATUS: INSTALLED. WE ARE CURRENTLY DOING BULK CHLORINATION TO MAKE WATER POTABLE BUT STILL WAITING ON SUPPORT KIT FOR ROWPU. TWO SMFTS ARE STILL IN TRANSIT AND LOCATION IS UNKNOWN. QTY/DAY LOCAL: BOTTLE DRINKING WATER UNLIMITED. DIST SYS STATUS: INSTALLED TREATMENT STATUS: INSTALLED FILTERS ON ORDER. ROWPU: ONE ON SITE/NOT OPERATIONAL PAGE 2 RHIDFKA0183 ERD STATUS: NOT REQ'D STORAGE CAPACITY: SEVEN 20 KGAL BLADDERS ON SITE AND INSTALLED. SANITARY LOCAL SYS: NOT AVAILABLE FIELD SYS: FOUR FIELD UNITS/INSTALLED/OPERATIONAL SHOWER/SHAVE STATUS: 4 INSTALLED/OPERATIONAL LOCAL SYS AVAIL/QTY: NONE WASTE MGMT SYS: LAGOON CONSTRUCTED. DISTRIBUTION SYSTEM COMPLETE. C. POWER STATUS: HIGH VOLTAGE SYSTEM IS OPERATIONAL IN TENT CITY AND IN OPERATIONS BUNKER AREA. POWER PLANT OPERATION 24 HOURS/DAY AND WE HAVE PEAKED DURING EARLY MORNING HOURS AT 1380KW. COMMERCIAL AVAIL/CAP: NONE DISTRIBUTION SYS CAP: INSTALLED/OPERATIONAL. GENERATOR QTY/CAP: 3 EA 5 KW, 7 EA 60 KW, 8 EA 100 KW, 4 EA 750 KW. WAITING ON REPLACEMENT FAN BOLTS FOR 1 EA 750 KW GENERATOR. 3 FAN BOLT SETS ARRIVED THIS WEEK. D. ATH HOSP STATUS: NO CHANGE FROM PREVIOUS SITREP. E. (U) VEHICLE STATUS: 1 EA M-35; 3 USAF 4X4 P.U. IN USE. PAGE 3 RHIDFKA0183
Document Page: First | Prev | Next | All | Image | This Release | Search